We at Stockwell Engineers feel it's important to keep the public up to speed on the progress of projects in their neighborhoods. If you'd like to be notified via email when a new update is released, please subscribe using this short form.


August 13th - Construction Update
Willow Street - Looking East at Creekside Ave Intersection Construction has been progressing well throughout the last few weeks. Since the previous update, Willow Street from Shebal Ave to Creekside Ave has been partially opened to traffic. A single lane of the roadway has remained closed in each direction to allow work on the median and the boulevards. The sidewalk from the east project limit to Creekside Ave has been completed. The contractor has been placing topsoil in the
jchristiansen7
Aug 132 min read


Road Closure Map Update!
See the below exhibit for an update on road closures starting July 20th!
jchristiansen7
Jul 141 min read


July 10th - Construction Update
This phase of Willow Street construction is nearing completion. The majority of the roadway pavement for this phase has been completed. Since the last update the contractor has completed the south two lanes of pavement, the turning lanes, concrete curb and gutter, miscellaneous concrete for intersections and approaches. D&G Concrete - Paving on Willow Street In the coming week the contractor plans to complete the remaining curb and gutter, sidewalk, and start the center media
jchristiansen7
Jul 101 min read


June 19th - Construction Update
The roadway has started to take shape in the last two weeks. Since the last update all of the remaining underground utilities have been finalized. The roadway has been graded and cement stabilized and gravel has been placed along Willow Street. The sidewalk on the south side of Willow Street has been started and will be finished in the coming weeks. Today the north two lanes of Willow Steet were paved from the existing concrete near Sanford's entrance to just east of Honeysuc
jchristiansen7
Jun 191 min read


June 5th - Construction Update
In the last three weeks there has been a lot of progress on the underground utilities on the project. Crews have finished installing the storm sewer for this phase of construction and the storm sewer boxes will be finalized in the coming days. The box culvert between Kwik Star and Casey's has been extended to the north and south. With the box culvert being extended it has allowed the temporary access road on the north side of Willow Street to be extended to the east toward Sa
jchristiansen7
Jun 53 min read


May 15th - Construction Update
Crews have completed the excavation of the excess material along Willow Street. The sanitary sewer on Willow Street has been completed for this phase of work and the underground utility crews are continuing on the storm sewer installation. There were various fire hydrant adjustments and water main stub outs that were completed since the last update. The topsoil and seeding work on Plainside Ave have been completed and crews have also poured the storm sewer boxes on the east e
jchristiansen7
May 151 min read


May 1st - Construction Update
The temporary access road was completed from Praireside Ave to the east portion of Willow Street. The temporary access allows customers access to local businesses and allows residents and emergency vehicles into the neighborhood. The removals on Willow Street have been completed, and crews are working to remove the excess material from the roadway. This work is scheduled to be completed by the end of next week. Excavation Work on Willow Street Sanitary sewer installation cont
jchristiansen7
May 11 min read


Willow Street Closure Update
Starting today 4/22 Willow Street was closed from Shebal Ave to the east side of Honeysuckle Drive. The Honeysuckle Dr/Willow St intersection will remain open during this phase of work. See the map below for updated closure. The map includes the detour route as well as local traffic routes. Project update: The sanitary sewer installation progressed from east end of the project (just west of Casey's entrance at Willow St) to the Shebal Ave/Willow St intersection. Completing t
jchristiansen7
Apr 221 min read


Willow Street Closure
Reminder that Willow Street is closed starting today (4/13) from the west side of the Casey's gas station to the east side of Kwik Star gas station. Road Closure Barricades - Looking West Crews have started performing removals and grading work along Willow Street. In the coming days, grading work will continue, and sanitary sewer installation will begin. The contractor has also started excavation for a horizontal bore near Tiger Way and Willow Street. This will not affect tr
jchristiansen7
Apr 131 min read


Street Closure Map
Good afternoon, everyone! The Harrisburg Street Closures map has been added to our website and is now available on the Schedule page. To view a larger version, please visit the Schedule page and click on the map. It will open as a full PDF in a new window. Please take a few minutes to review the map and plan your routes accordingly. Let us know if you have any questions. Thank you!
Stockwell Engineers
Apr 11 min read


Stockwell Engineers
Mar 190 min read
bottom of page