May 1st - Construction Update
- jchristiansen7
- May 1
- 1 min read
The temporary access road was completed from Praireside Ave to the east portion of Willow Street. The temporary access allows customers access to local businesses and allows residents and emergency vehicles into the neighborhood.
The removals on Willow Street have been completed, and crews are working to remove the excess material from the roadway. This work is scheduled to be completed by the end of next week.

Sanitary sewer installation continued west on Willow Street nearing the Creekside/Willow intersection. The sanitary sewer for this portion of work is on track to be completed by mid-next week.

Storm sewer installation was started on the east end of the project and has continued up to the Praireside/Willow intersection. Once the sanitary sewer is completed the crews will pick up the storm sewer and continue it to west on Willow Street.
All of the concrete work is completed on Plainside Ave, and topsoil has been placed behind the curb and gutter and around the new sidewalk that was installed. Crews still have cleanup work to perform but this area will be seeded in the coming weeks.
The horizontal bore near Minnesota Ave is nearing completion and will be completed over the weekend or early next week.
The contractor plans to start concrete work on Shebal Ave starting the week of May 4th. This work will extend about 160 feet south on Shebal Ave.